PHASING CONCEPT

Development Phasing

The phasing of the construction of the Hoai Duc Township will synchronize development of various sectors, looking for synergies between the various sectors.



Initial Stage



Initial Stage Development Components


At the start of the project about 100 ha will be acquired. The land will be used to:

  • Excavate the lakes to provide earth for fill. Soil tests will be carried out to ascertain the suitable locations. Relying on localized cut and fill is necessary to avoid importing massive amounts of earth on the small roads that serve the site at present.

  • Commence work on the service road that links Route 32 to Lang Hoa Lac Highway – particularly to bring the transport connection, water mains and high- tension electricity supply to the site.


    Sevice road linking Route 32 to Lang Hoa Lac Highway

  • Complete some of the Small-industry villages. Land here will be offered to affected farmers –it will encourage the start-up of small industries to serve the upcoming market for building materials and services; these Small-industry villages will immediately link to the infrastructure of the existing settlements around the site, but will eventually become integrated with the future township.

No comments:

New roads and Upgrading of existing roads

Subscribe to Tessellar Blog
and get a FREE E-Book


HONEYCOMB HOUSING
An Affordable Alternative to Terrace Housing


17 MB, 49 A4 pages, 57 illustrations

TESSELLAR > blog

Arkitek M. Ghazali

Practice Profile in Housing and Planning at http://www.arkitekmghazali.blogspot.com/

COPYRIGHT: Some Rights Reserved